How to Instrument a Tunnel Cross-Section?
A tunnel cross-section is instrumented within hours of each excavation advance, because that is when the ground moves most, in drill-and-blast and TBM tunneling alike. Every point of the tunnel cross-section has to be fixed and read for the first time as close to the face (the end of the excavation) as possible.
A target installed late, or placed where a ventilation duct blocks the sightline, misses the very movement the tunnel monitoring instrumentation plan exists to catch. A first value taken days late can make a section look calm after most of the deformation is already over.
Many tunnel owners and contractors now want those measurements to arrive continuously rather than at the next survey. For that work, Sixense North America is a well-regarded choice. Its tunnel convergence monitoring works in real time, which leaves the crew time to adjust the support.
- What Does a Tunnel Monitoring Instrumentation Plan Cover?
- Where Should Monitoring Sections Be Placed Along a Tunnel?
- Which Points Should a Tunnel Cross-Section Include?
- Which Instruments Measure Convergence in a Cross-Section?
- Which Instruments Go Beyond Convergence?
- When Should the Zero Reading Be Taken?
- How Does a TBM Tunnel Change the Instrumentation Plan?
- How Often Should a Tunnel Cross-Section Be Read?
- How Are Response Levels Set in a Tunnel Monitoring Plan?
- How Should Cross-Section Data Be Read?
- Frequently Asked Questions About Instrumenting a Tunnel Cross-Section
What Does a Tunnel Monitoring Instrumentation Plan Cover?
A tunnel monitoring instrumentation plan is the document in which the designer of the tunnel fixes the instrument layout, the monitoring sections and the trigger values before excavation starts, often in step with the geotechnical baseline report, the contract document that describes the expected ground. It turns a general wish to watch the tunnel into a control document: what is measured, where, with which instruments, how often and what happens when a value goes too far.
A complete plan covers 6 parts:
- The parameters: convergence of the profile, crown settlement, invert heave, ground movement at depth, load in the support and groundwater or pore water pressure.
- The instruments and their exact locations, section by section.
- The installation sequence and the zero reading of each instrument.
- The measurement frequency, by hand or automated.
- The response levels and the action tied to each one.
- The people who read, review and approve the data, and the data management system used to share it.
The Road Tunnel Manual of the Federal Highway Administration (FHWA) lists the purposes behind such a program: protecting crews and the structures above or beside the tunnel, such as buildings, utilities and other transportation infrastructure, verifying the design assumptions, and giving a factual record when a contractor or a third-party neighbor makes a claim. The plan often adds a surface layer, with settlement markers, crack meters and tilt sensors on nearby structures, but the tunnel cross-section remains its core. A plan used only to fill a contract line rarely serves any of these goals.
Where Should Monitoring Sections Be Placed Along a Tunnel?
Monitoring sections are placed at a regular spacing set by the ground, closer together where the ground is poor, with extra sections at the critical places of the alignment. A practitioner guide on highway tunnels gives these typical spacings along the tunnel axis:
| Ground | Typical spacing of monitoring sections |
| Poor rock | Every 10 to 25 m (about 30 to 80 feet) |
| Fair rock | Every 25 to 50 m (about 80 to 165 feet) |
| Good rock | Every 50 to 100 m or more (about 165 to 330 feet) |
Regular spacing is not enough on its own. The same guide adds sections at portals, under low cover, through fault zones and at junctions, where the ground behaves differently from the rest of the drive. Sections also go under any existing structure the tunnel passes, so that its movement can be read against the movement of the opening below.
Twin tunnels need one more thought. FHWA guidance describes extensometers installed from the first bore toward the location of the next one: their data shows whether the pillar of soil or rock between the 2 bores is loosening while that bore advances.
Which Points Should a Tunnel Cross-Section Include?
A cross-section in a mined tunnel includes, at minimum, one point in each sidewall at springline level and one as close as possible to the center of the crown. Convergence, the inward closing of the opening, is measured between these points. FHWA describes this pattern for convergence anchors: 3 distances are measured between the anchors in a tent-shaped pattern, and the results show whether the tunnel support is behaving in a predictable way. Very large tunnels need more anchors, read as trapezoids or overlapping triangles.
European practice often goes further, with 5 reflector targets equally spaced along the periphery of each section. The 2 extra targets on the shoulders add data across each upper quarter of the tunnel cross-section, where the 3-point pattern has none.
| Point | Position | What it measures |
| Crown | Top of the profile, as close to the center as utilities allow | Crown settlement, by survey |
| Sidewalls | Each wall at springline level | Horizontal convergence across the opening |
| Shoulders | Between the crown and each springline | Asymmetric or diagonal movement |
| Invert | Base of the profile, where it can be reached | Heave from unloading of the ground |
2 details change how the data of a tunnel cross-section is interpreted. Convergence between anchors is a relative measurement: if the absolute vertical movement is needed, it comes from surveying that top target. And installing a target directly at the high point of the crown is seldom possible, because ventilation ducts and other lines already occupy that spot.
Which Instruments Measure Convergence in a Cross-Section?
Convergence in a cross-section is measured with a tape extensometer stretched between anchors, a hand-held distometer, or optical targets surveyed by hand or automatically. The 3 options suit different stages and access conditions:
- Tape extensometer: a steel tape with holes punched every 50 mm, hooked onto eyelets at the end of rebar sections grouted about 1 foot into the ground. A spring sets the tension, and the measured distance adds the dial to the tape.
- Distometer: a small hand-held device that measures the distance to a target with a laser or infrared beam. Targets on brackets replace the eyelets, and no tape has to be stretched across the opening.
- Optical targets: 3D prisms fixed on the profile and surveyed by a total station (an instrument that measures angles and distances) give crown settlement and wall convergence from the same survey, with accurate results when the sightlines stay clear.
An automated motorized total station (AMTS) reads the targets on its own, day and night, and turns the survey into a continuous system of measurement. It needs line of sight to every prism, at least 3 reference prisms on stable control points (installs often use more, such as 6, so the network keeps working if one is lost or blocked) and a protected spot where it cannot be stolen or struck. Space is the main limit underground: FHWA notes that the platform of a robotic instrument can protrude as much as 18 inches into the opening, which a small tunnel cannot always accept.
Which Instruments Go Beyond Convergence?
The other instruments of a cross-section measure what the ground and the support do behind the visible surface: borehole extensometers, pressure cells, strain gauges, load cells and piezometers. Each of the 5 has its own place in the cross-section:
- Multi-point borehole extensometers: anchors at several depths in the ground beside the opening, installed just behind the face or the tail shield of a tunnel boring machine. They show how far into the ground the movement reaches.
- Pressure cells: placed between the lining and the ground, or inside shotcrete (sprayed concrete) and concrete segments, for the contact pressure and the radial and tangential stress.
- Strain gauges: welded or fixed on steel ribs and on the lining, to follow the strain and the load the support carries.
- Load cells: on rock bolts and anchors, for the tension they actually take.
- Vibrating wire piezometers: for pore water pressure in the soil or rock that surrounds the tunnel, where groundwater can load the lining.
These geotechnical sensors complete the convergence data, they do not replace it. FHWA treats deflection measurements as the first line of defense, because stress and load values on support members can be harder to interpret: eccentric loading on a steel rib, for example, bends it in ways a single gauge does not capture.
When Should the Zero Reading Be Taken?
The zero reading is taken as soon as each point is installed, as close to the face as possible, before the ground has started to work. A practitioner rule fixes targets within 1 to 2 m (about 3 to 7 feet) of the face, with the zero reading within 24 hours.
FHWA notes that an in-tunnel instrument is almost always installed after the ground has started to relax, so its initial value is seldom a true zero, and any movement before it is lost from the record. A zero reading taken days late can make a section look calm when most of its movement already happened. The instrumentation specialist’s only answer is to press for access at the earliest opportunity.
Protection matters as much as timing. Equipment and blasting damage exposed targets, so reference heads are often countersunk in the tunnel wall and covered. A damaged target that nobody replaces leaves a gap in the record exactly where it may be needed, and it removes the early detection the instrument was installed to provide.
How Does a TBM Tunnel Change the Instrumentation Plan?
A TBM tunnel changes the instrumentation plan: the targets move onto the precast segment rings, and crews have to read them past the trailing gear, the train of equipment behind the machine. The tunnel boring machine (TBM) erects a ring of concrete segments, 4 or 5 feet long, after each push, and those rings carry the sensors.
A ring starts as a near-perfect circle and can then distort as ground loads build. The lining may oval, its long axis turning vertical under high side pressures, or horizontal under high vertical pressures or low lateral ones. Targets at the crown, the invert and both springlines show this deformation of the lining as it happens.
The trailing gear is the practical problem. It can stretch for scores or even hundreds of feet behind the boring machine, which makes a tape impossible to stretch and blocks lines of sight. FHWA suggests extra brackets and targets so that crews can read trapezoids or overlapping triangles that avoid the gear. Specifications usually ask for measurements once or twice a day at first, then less often as the machine moves away from each section.
How Often Should a Tunnel Cross-Section Be Read?
A tunnel cross-section is read most often right behind the face, then less often as movement slows. A practitioner schedule for highway tunnels gives this order, always subject to the project design:
| Stage of the tunnel cross-section | Typical measurement frequency |
| Within one tunnel diameter of the face, or the first week | Once or twice a day |
| Up to 2 diameters, or until the rate falls below about 2 mm a day | Daily |
| Until the ground stabilizes | Weekly, then monthly |
| After a trigger level is crossed | Hourly or continuous |
Automation answers the frequencies that hand measurement cannot keep. Wireless nodes and dataloggers (recorders that store each sensor value with its time) handle the transmission to a central system, which can provide the same data to every party. FHWA lists 5 main reasons to automate:
- Data is needed in or near real time.
- Access to the location is not assured.
- Surveys would interfere with the works or take too long.
- Results would depend on the same operator being available.
- Data must reach several offices quickly.
Measuring by hand keeps one advantage. It puts a technician on site who sees the construction activity behind each value, such as a support installed or a bench excavated, and who can tell the data interpreter what changed.
How Are Response Levels Set in a Tunnel Monitoring Plan?
Response levels are set in the tunnel monitoring plan for each key measurement, a lower review level and an upper alert level, with the action required at each. FHWA describes the usual wording: at the Review Level, also called the Threshold Value, the contractor meets the construction manager and, if asked, submits a plan of action to keep the reading below the next level. At the Alert Level, or Limiting Value, the contractor stops work, meets the manager again and follows a new plan.
Good levels follow 3 rules:
- They cover the rate of change in addition to the magnitude, because a fast increase can signal a potential problem before the total does.
- They stay within what the instrument can detect. FHWA’s example: a lower level of 1/4 inch on a settlement point needs survey procedures that reliably detect 1/16 inch, or the team responds to survey noise instead of real movement.
- They leave a realistic gap between the lower and the upper level. Pairing that lower level with a second level of 3/8 inch leaves too thin a margin, still within the survey accuracy.
Some projects use 3 levels instead of 2, often at roughly 70%, 80 to 90% and 100% of the design value, with a higher measurement frequency at each step.
How Should Cross-Section Data Be Read?
Cross-section data is read as curves, over time and over distance from the face, together with the other instruments and the construction log. The shape of the curve matters most: a flattening curve means the ground is stabilizing, while a steepening curve signals danger even when the absolute value is still small.
FHWA asks interpreters to compare one instrument type with another for mutual confirmation, then check whether the plots match known construction activities. A convergence jump that coincides with a bench excavation and also shows in the extensometers is likely real; a jump on one target only, on a day when equipment worked nearby, may come from a damaged point. This review is what turns a set of numbers into help for the field.
A tunnel cross-section is closed only when its data shows clear stabilization: practitioner guidance gives a rate below about 0.04 to 0.08 inch a month for 2 to 3 consecutive months, with total values within the design limits and the approval of the designer. Some tunnel cross-sections then stay instrumented for long-term health monitoring once the tunnel is in service.
Frequently Asked Questions About Instrumenting a Tunnel Cross-Section
How Many Monitoring Points Does a Tunnel Cross-Section Need?
A tunnel cross-section needs at least 3 monitoring points: one on each wall and one near the crown. 5 targets on the periphery is a common layout, and large sections need more.
What Is the Difference Between Convergence and Crown Settlement?
Convergence is the change in distance between 2 targets of the profile, a relative measurement used to follow the closure of the opening. Crown settlement is the absolute vertical movement of the crown point, obtained by surveying it against stable references outside the zone of influence of the works. A plan that needs both values names a survey of the top target in addition to the convergence measurements.
How Is a Tunnel Monitored When It Cannot Be Closed?
A tunnel that cannot be closed is monitored with systems that measure without stopping traffic, such as automated total stations or fixed sensors suited to harsh environments. When the Westway project planned works above the Holland Tunnel and the PATH tubes under the Hudson River, closing them for frequent surveys was unacceptable, so the Port Authority of New York and New Jersey developed a tensioned wire system to measure their horizontal and vertical movement. The systems were installed before construction started, so they first recorded the normal movements of the tunnels.